The Friday Retro, In Depth
How Synx Data Labs grades a week of engineering work with ccxp-skills — four possible outcomes for every committed task, the metrics snapshot that replaces memory with numbers, the chronic-bump escalation that stops a task from losing the coin flip forever, and the one-skill-per-week cap that keeps process fixes from becoming their own project.
Last week’s post covered /drive, the loop that turns one claimed task into one merged pull request. This post covers the other bookend of the week: /retro, in ccxp-skills — what runs every Friday to check whether the week actually delivered what Monday’s IPM committed to, using real numbers instead of whoever remembers the loudest. Unlike the retro itself, the Monday IPM is opt-in rather than something /ccxp auto-triggers, so the task-by-task grading below is dormant by design — not broken — on a week where no IPM ran.
Four outcomes, not a pass/fail
The core of the retro is mechanical: every task that made it onto that week’s IPM file (when one ran) gets classified into exactly one of four outcomes. Shipped means a pull request merged and the task closed as done. In flight means work started — status is in-progress or in review — but nothing merged yet; it carries over as next week’s priority. Partial means commits exist on a branch with no pull request open, or a pull request opened and then stalled for three days with no movement. Dropped means the task never got past “committed to” — still open, never started.
For anything shipped, the grade compares the estimate against real elapsed time — a pull request’s actual created → merged timestamp, not a developer’s memory of how the week felt. And because an estimate can drift mid-week without anyone writing down that it did, the retro also pulls each task file’s own git history to reconstruct the arc: filed at one estimate, held all week, or revised up or down along the way. An estimate that was revised upward and then roughly matched reality reads very differently from one that was quietly cut to fit the time that was left, even though both can end up looking identical if you only look at the final number.
The bump that won’t fix itself
A single dropped task is unremarkable — priorities shift, a week gets busy. Three in a row is a different signal. The retro cross-references the current week’s focus list against the previous two, and if a task shows up Dropped on all three, it gets flagged as bumped three times and moved to the front of the backlog automatically via /top — there’s no separate priority field to set, since a task’s position in dev/TODO/queue.md is its priority (next week’s post covers that choice directly) — no human has to notice the pattern. The point isn’t to force the task through — a human can still consciously park it — it’s to stop a task from quietly re-losing the same coin flip every single Monday indefinitely just because something else always looks more urgent in the moment.
What the numbers actually say
Alongside the task-by-task grading, the retro computes a metrics snapshot for the week: CI pass rate and how it moved against the prior retro, average pull-request cycle time, how many escalations fired and how many got resolved, and backlog size. One section is specific to running a build loop unattended around the clock: how many minutes a day the cron actually spent doing real model work, what it cost, and — maybe the most telling number of the group — the ratio of hourly checks that found something worth acting on versus checks that correctly did nothing. A ratio sitting near zero against a backlog that keeps growing anyway is a sign the automated checks are missing real signal, not that there’s genuinely nothing to do.
One skill, at most, per week
The retro doesn’t just grade the product work; it grades the tools doing the work. Every week, it ranks whichever skill caused the most friction — too many review round-trips, a recurring CI failure pattern, a task that kept getting bumped because the planning skill mis-scored it — and acts on exactly one. If the fix is a bounded, unambiguous prose edit, it goes up as a real pull request against ccxp-skills and goes through the same independent review as any other change, never a direct merge. If the fix would touch the skill’s actual contract, or the right answer isn’t obvious, it gets downgraded on the spot to a filed task for a proper design pass later, rather than a same-day rewrite. The cap is deliberate: a Friday retro that turns into an open-ended skill-engineering session has stopped being a retro.
Closing the loop
Whatever comes out of all of this — a new action item, a priority escalation, a skill fix drafted or filed — lands as a fresh entry in dev/TODO/, which is exactly the pool Monday’s IPM draws its next commitment from. The retro doesn’t just look backward; it’s the mechanism that feeds the next week’s planning, closing the loop the series opened with the IPM post.
The retro has also kept growing new sections of its own since it first shipped: a pass that evaluates whether previous process experiments actually worked out, a rolling velocity number used to project how long new work will take, a trailing code-quality scoreboard that watches for regressions without yet hard-blocking on them, and a scan that checks whether some other, unrelated skill set has already solved a problem better than we have. None of those change the core shape above — they’re additional questions the retro has learned to ask, on the same weekly cadence, about the same week’s evidence.
That’s the other bookend: four outcomes instead of a vague sense of “good week” or “bad week,” a bump counter that escalates on its own, a numbers-first metrics snapshot instead of institutional memory, and a process-improvement loop that is deliberately capped at one change a week so it never becomes the biggest project on the board. Next week’s post closes out this series with the philosophy underneath all six of these mechanics posts — why the backlog is plain markdown files in a git repo, not a ticket in a separate system, and why that choice is what makes everything described so far actually auditable.